New Medievalism Overides Popular Sentiment On I-395 NYA Tunnel Extension:

The recent poor planning on the Center Leg/ 3rd Street Tunnel Air Rights Project ties directly into the disregard of popular opinion favoring extending I-395 to the northeast via a new tunnel.
Citizens favor I-395 tunnel.  

Yet the U.S. National Capital Planning Commission alas, favors sticking heads into sand with unworkable parochialist-medievalist bias against outsides and automobiles- pretending that NYA does not connect MD route 50 freeway with I-395. 
Failing to extend I-395 is NOT about saving neighborhoods, but rather about a parochialist mentality to instead continue to place a disproportionate traffic burden upon less affluent neighborhoods


The I-395 Capitol Crossing Air Rights Project assumes that the freeway will never be extended, failing to even discuss the matter and giving away 50% of its right of way, including pinching the median shoulders without mention to safety-operation ability of the freeway.

It acts as if there was no recent planing efforts to extend the freeway as a tunnel that would rescue the urban neighborhoods around and along New York Avenue from the freeway levels of traffic using that Avenue from 4th Street eastward as the de-facto freeway- neglecting that it connects to the Route 50 freeway that heads to Annapolis, and its interchange with the Baltimore Washington Parkway.

 1996 I-395 New York Avenue Tunnel proposal to 7th Street NE

Extending I-395 to the northeast was not simply an idea abandoned during the mass 1970s freeway de-mappings - despite such freeways having been massively re-routed and re-designed to meet criticisms of earlier planning.

It's an idea that was revived during the 1990s under the direction of the D.C. Office of the Mayor, when the Mayor was Marion Barry, who had got much of his political start from being involved with the organized opposition to the official freeway planning during the 1960s with the group ECTC, serving as one of its Vice Chairmen.


The plans in place just prior to the de-mappings, for a cut and cover tunnel alongside New York Avenue, would have displaced (and replaced) about 600 Victorian townhouses in the area just north of New York Avenue between 4th Street NW and North Capital Street (including a one block row on New York Avenue's north side eastward to Ist Street NE town down during the administration of DC Mayor Anthony Williams).

 1971 DeLeuw, Cather, Weese
Tunnel alongside New York Avenue

The 1971 design for a cut and cover tunnel alongside New York Avenue would have been 10 lanes (2x5) wide.  Of these, 6 (2x3) would connect with the 8 lane Center Leg; 4 (2x2) with the 6 lane I-66 K Street Tunnel; and 2 (2x1) connecting the Center Leg and the K Street Tunnel.

 


The Center Leg as then built was designed for 8 lanes (2x4), plus extra space in the northbound carriageway for a lane westward to the I-66 K Street.- with its construction started started in 1975 before the de-mappings of the connecting highway links.  Today it only appears as a 2x2 lane structure due to the addition of a set of non-load-bearing tunnel walls with the 1983-1986 finishing project, which could thus be removed without compromising the structure.

The tunnel design unveiled in 1996 with the New York Avenue Development Report for the further extension to the  north-east, extends not  alongside but rather directly beneath New York Avenue, with a curved transition to the Center Leg wrapping behind the rear of the Bibleway Church complex, using existing open space, hence requiring no building displacement.  Thus, in contrast to the '1971' plan that would have displaced and replaced 600+ dwellings, it would displace 0 dwellings.

That would avoid the likely criticism of the 1971's building displacement.

But it would contain a trade-off, with the curved tunnel transition to and from the Center Leg that would wrap behind the rear of the Bibleway Church complex with geometrically inferior geometry- perhaps 30 rather than 50mph- somewhat deficient for an interstate highway.

Perhaps that's the reason why the report refrains from calling this tunnel an extension of I-395.


1996 New York Avenue Development Report
"Long" Tunnel beneath New York Avenue

The 1996 cut and cover tunnel design would have been 4 lanes (2x2) wide, with each lane 12 feet wide, with or without shoulders, continuing from the Center Leg. 

It would include a set of cut and cover tunnel segments connecting westerly, not to an I-66 K Street tunnel but rather as an underground connection to the new Convention Center.  Although the report included no detailed drawings, it is apparent that this extension would have required demolishing the non-load-bearing wall at least in the northbound Center Leg Tunnel, bringing it to 3 lanes. northbound.

 1996 NYA Tunnel- western connection to Convention Center

While the 1996 New York Avenue Tunnel was designed to fit entirely within the 134 foot wide right of way of New York Avenue in order to displace no buildings, no reason was given why it was shown with only 4 (2x2) rather than 6 (2x3) lanes, as that right of way is 130 feet between building lines.

Although not explicitly called an I-395 extension, the 1996 design is here shown with 8 foot right hand shoulders, each with a 3 foot wide 1 1/2 wide barrier separated walkway, with 2 travel lanes in each direction, but with no left hand shoulders, with a median of a center wall with jersey barriers together measuring 5 feet- all flanked by 2 1/2 foot wide outer walls= and 83 foot wide tunnel box.

As U.S. FHWA specifications for interstate highways require 3 meter (9.84252 foot) outer shoulders and 1.5 meter (4.92 feet) inner shoulders for tunnel segment, this design would not qualify- needing essentially a 5 foot wide set of inner shoulders plus nearly another 2 feet for each o the outer shoulders- all in all adding another 14 feet to the 83 foot given width: 97 feet for an interstate tunnel with 4 travel lanes or 121 feet for one with 6.

Both versions with or without right hand shoulders would be shown with the option of a 'short' (2,100 foot) length, with it eastern portal between North Capitol Street and Florida Avenue.  

The version with the 8 foot right shoulders would be also shown with a 'long' (4,400 foot) length, emerging east of the B&O/Red Line railroad at 6th Street NE.

The costs given for the 2,100 foot long, no shoulder and 4,400 long, with 8 foot right shoulders versions, were $340 and $600 million respectively.

1996 "I-395" Tunnel beneath New York Avenue 2x2 lanes plus shoulders
Note drafting dimension lines at left drawn as if to suggest a 2x3 lanes version

This 1996 design New York Avenue Tunnel was designed to share this right of way with a concurrent or future addition of an underground WMATA rail line.


The option of constructing the highway tunnel first would include extra deep wall extensions allowing subsequent construction below, here shown as the addition of a drilled WMATA tunnel.


Such a WMATA rail line could be built as a covered tunnel within the ample rail corridor paralleling the north side of New York Avenue to the east of the existing B&O/Red Line railroad corridor.

So could an eastern extension of the highway tunnel.

Both ideas are combinable with the idea of decking over the rail properties, with a new linear park along new York Avenue and an extension of the street grid supporting lots of new development and ending the railroad bisection.

However the report and the subsequent official planning would give little if any discussion to any of that.


This "New York Avenue Development Report" dated November 1996, was largely crafted by Ron Linton, and is often referred as the "Ron Linton report".

1996 'short' tunnel emerging between North Capitol Street and Florida Avenue

1996 'long' tunnel emerging at 6th Street NE

1996 'long' tunnel emerging at 6th Street NE


It was followed with a 1998 proposal for an even longer version extending further east to emerge at Montana Avenue.

Doing that would leave only the intersection with Blandensburg Road before New York Avenue flows into the Route 50 freeway physically standing between a full traffic light free road link between I-395 and Route 50, with its interchange with the Baltimore-Washington Parkway.

Public sentiment by any indication favored the longest tunnel feasible.  That would separate regional and local traffic, with the former comprising the bulk of the traffic into  tunnel, allowing surface new York Avenue to become less of a highway and more as a city street.

New York Avenue carries roughly 77,000 vehicles daily.

A tunnel would accommodate this traffic and even more - particularly with 6 rather than the artificially contained 4 - while giving the local neighborhoods the avenue back as a local street or boulevard.

But as was already plainly obvious with the artificial restriction to only 2 lanes in each direction connecting to a Center Leg designed for twice that number- the official planning was being steered elsewhere- to the idea that if we just don't build the freeway facility that the traffic will just 'go-away'

Such a facility it would be argued, either because it was 'too expensive' or because we just should not accommodate people from outside the neighborhood- never mind that such an attitude was directly contrary to the sentiment of the locals seeking to make New York Avenue itself as more of a boulevard and less of a de factor expressway!

Such a facility would cost in the low billions, serve as the gateway to what is the Nation's Capitol, and serve as a basis for significant new air right development atop locally divisive railroad and rail yards, and even be funded in part by tolling made all the more practical by non stop easy pass electronic tolling.

Nonetheless, the planning would be steered to a dogma against building any new urban freeways regardless of design or tunneled or not:  an attitude that may not be consistent with local urban opinion against 1950s style elevated highways, but which is being deeply propagandized into professional "urbanist" thinking that would better be labeled  new or neo-medievalists.

Such is what occurred the two main subsequent planning studies by the District Department of Transportation, the other by U.S.National Capital Planning Commission, with officials back-tracking by too quickly dismissing tunnel as 'too expensive' while neglecting ideas making such more practical.

The DDOT study was officially named the "New York Avenue Corridor Study".

Citizens:
https://comp.ddot.dc.gov/Documents/New%20York%20Avenue%20Corridor%20Study.pdf
Hi Rick

I live on R Street NE.  I think the best solution to the NY Avenue traffic nightmare is to build a tunnel from the BW Parkway to the 395 tunnel.  that's all that is needed to fix the problem.  95 percent of the NY Avenue traffic simply wants to get to Virgina and Maryland.  they're aren't interested in DC- they don't want to stop.

Every day I ride my bicycle to work along NY Avenue headed south and "no one" continues past the 395 turnoff- no one is going into DC.  Every night coming home it is gridlock- cars stick on NY Avenue.  Make these people pay for changes.

All these "one person in a vehicle environmental destroyers come from Maryland and Virgina- why not make them pay for the improvement?  If the city had been charging rush hour commuters a quarter each way for the past 5 years you would have a billion dollars for the upgrade now- $32 million per year.

Every day we have 175, 00 cars sitting in gridlock, destroying our environment and chocking our air- all because of outdated planning.

If we leave the existing roads for local traffic there is no need to change them.  plat trees don the center of NY and Florida avenue.  Plant trees elsewhere.  Let all the through traffic go underground.  That way we don't have to see or smell them!  The amount of pollution and gridlock is disgusting and our neighborhood is suffering because of it.  the arteries need to be unblocked and new trees planted.

Once the tunnel is complete and we have only have local traffic to deal with, we should bring the neighborhood back to the way it was designed by reinstating the beautiful traffic circles and adding a new one at NY and Florida.

A bridge over Florida Avenue- ridiculous.

And don't tell me you can't put a tunnel under railroad tracks

Regards
Scott Porter
237 R Street NE
Washington, D.C. 20002
sporter@imf.org
Rick, I reviewed your meeting notes from the final public meeting and I thought that your representative of our viewpoint  regarding the NY/FLA Avenue Bridge was fairly accurate however, in responding to the cost comparisons between the bridge vs the extended tunnel option, I think that you should have mentioned the possibility that the land and development space gained form an extended tunnel option could have additional possible economic impacts for  District, and these impacts would reduce the $300-$400 million dollar cost between the two alternatives- Mike

Micheal Weil
michael.wel@ncpc.gov

Designing the tunnel to be easier  to construct and to support new development was a set of major ideas neglected by the officials involved with this planning.


Placing the tunnel directly beneath New York Avenue was to avoid displacing buildings, yet costlier than one alongside.

Yet why would this planning subvert the idea of a longer version extending east of the B&O/Red Line that would be easier to construct and easier to accommodate new development particularly via decking over the chasm of railroads?

Rather than extending the tunnel east directly under New York avenue, why not instead alongside via the existing of a clear strip of under utilized parking lots there between the Avenue and the adjoining enormous railroad corridor.

Constructing the tunnel there would not only be immensely less complicated and thus less expensive than beneath the Avenue, and easier for not conflicting with traffic, but would provide the start for a decking over of the adjacent railroad that would create large amounts of new land for a new linear park with new surface development via extending the street grid to eliminate the existing railroad bisection.   After all we hear so much about the need for new urban infill development.  And we hear about how grade separated roads divide cities- with highways anyway, but not vast rail yards- go figure.  Yet the official planning would remain weirdly obtuse to that idea.

Instead, post 2000 official planning would steer greater attention upon 'short' tunnel options that would emerge between North Capitol Street and Florida Avenue, with an emphasis upon an idea that would not be popularly received, of an elevated viaduct to carry the express lanes of New York Avenue to cross over Florida Avenue.


To its credit the DDOT study included an interesting short tunnel for the New York Avenue express lanes to cross beneath Bladensburg Avenue.



As this 1996+ planning artificially constrained itself with the obtuseness towards placing the tunnel east of the B&O alongside New York Avenue, and in constricting the width to avoid interstate spec shoulders and to throw away the additional 50% capacity despite the available building-free right of way beneath the Avenue and within the northern Center Leg Tunnel hidden by the non-load-bearing add on walls, no other tunnel designs were considered.

Despite that, and the added factors of:
- short term disturbance to traffic of constructing a cut and cover tunnel beneath the heavily traveled New York Avenue approach to the existing I-395 truncation, and

- the permanent poor geometry of the 'Ron Linton' design curved transition tunnel behind the Bibleway Church complex,

I was told that my idea of a gently arcing tunnel beneath the intersection of New Jersey and and N Street and then a double stack under O Street could not receive any considered because it would displace some 33 or so dwellings (a 95% reduction from the 600+ of the 1971 design), because the project somehow had to displace zero dwellings.  Thus, that idea appeared nowhere in this formal planning process.
 
Fascinating- a study that neglects the potential of a traffic tunnel to make a corridor actually more conducive to development, let along the option of routing it alongside New York Avenue that would make it less complicated and less expensive to construct.

Noting the levels of traffic, along with the numerous citizen's comments, the DDOT report endorses the idea of an I-395 extension via a tunnel.
Report Recommendation:

It would be highly desirable to separate regional and local traffic in this area.

The study recommends that I-395 be extended by means of a tunnel under New York Avenue from its current terminus at 4th Street NW to east of North Capitol Street.

With regional traffic corridor (thought to be half the traffic currently on New York Avenue in that area) removed, the cross section of New York Avenue could be modified to remove one lane of traffic in each direction.  This would allow for extensive street-scape improvements and permit on street parking.
Not leaving well enough alone, U.S. National Capital Planning Commission (NCPC) chimed in with its 2006 "New York Avenue-Florida Avenue Charrette" consisting not of citizens but rather of a selected group of paid consultants.


http://www.ncpc.gov/DocumentDepot/Publications/NYFLACharette_2006.pdf
Howards Decker FAIA
Project Directer Ehrenkranytz Eckstut & Kuhn, Washington DC

Louis J Slade PE TOE
Vice President and Principle
Goove/Slade Associated
Washington DC

Antia B Morrison MPP
Principle Bay Area Economics
Silver Spring MD

Raymlond E. Peloquin AIA CARB Associates
Baltimore MD

Don Stull FAIA NCARB
President and Principal, Stull & Lee Inc Boston MA

Benjamin Tang
Major Bridge Specialists Leader US Federal Highway Administration Washington DC
This considered 3 options.  All included a tunneled extension from the I-395 Center Leg following the 1996 Ron Linton routing wrapping behind the rear of Bibleway, and continuing beneath New York Avenue, and eliminating the existing North Capitol Street underpass:
- "Bridge Alternative": short tunnel with portal just east of North Capitol Street than arising to bridge atop Florida Avenue

- "At Grade Alternative" : short tunnel with portal just east of North Capitol Street

- "Tunnel Alternative" : longer tunnel with portal emerging east of the B&O railroad.
Noting the traffic counts indicating a high percentage of a regional nature, continuing from the Route 50 freeway and the Baltimore Washington Parkway to the I-395 Center Leg or visa versa, they note the benefits of a tunnel to provide significantly reduced surface traffic levels upon its parallel segment of New York Avenue

Nonetheless, despite the local urban support for a tunnel, particularly the concept of one significantly longer, the NCPC "charrette" (charade) consultants overwhelmingly chose to disregard that in favor of such points as these:
- the DC street network exists to serve District residents and neighborhoods first and those who work in the District second.  Give much less priority to accommodating regional interstate traffic.  Decker, Morrison, Peloquin, Slade, Stull
- Focus on moving people- not cars  Encourage a bias against the automobile.
Decker, Morrison and Slade
- removal of the current regional through traffic-volumes would create opportunities for mixed use development Decker, Morrison, Peloquin, Slade, Stull
- To discourage use of New York Avenue/I-395 for regional through traffic Decker, Slade
- consider tolls or congestion pricing Decker, Slade
- Consider truncating I-395 at Massachusetts Avenue Decker
- Consider pairing the New York Avenue and Massachusetts Avenue ramps: off only at New York  and on-only at Massachusetts. Decker
- Use the opportunity of the Woodrow Wilson Bridge and I-295 improvement to discourage use by regional pass-through traffic on New York Avenue. Decker, Sade

Consultants Decker, Slade, Morrison, Peloquin and Stull all criticize all three as encouraging through traffic.
Move people not cars?  
People in cities move in cars unless on foot or bicycles- ridiculous ideology useless except for distracting from the economic exploitation for shirt term profit

The only consultant to refrain from so disgracing himself is Benjamin Tang.

All of the other consultants, Decker, Slade, Morrison, Peloquin and Stull subscribe to the parochialism-medievalism plaguing our Nation's Capital.

Thus, years of official planning with local citizen sentiment overwhelmingly favoring a longer tunnel would be subjugated to a new medievalism that claims to favor local neighborhoods while actually disregarding them.

Most of the popular local opinion was pro tunnel, specifically pro-longer tunnel, and even pro development given the ample railroad related brown-fields.

Yet while such was the sentiment of the urban people, the 'urbanist' professionals here would pay lip service to an idea that only local residents mattered; and that outsiders should have to take a longer route- and one through the less affluent southeast.

Never mind the reality that New York Avenue is the direct extension of the Route 50 freeway and that a tunnel could be fund-able by tolls and rail-yards air rights development.

The paid consultants here would primarily take positions against such city residents support for a tunnel for regional traffic in order to accommodate the more broad goals of accommodating regional traffic and local neighborhood concerns, in favor of a dogmatic parochialism acting oblivious to the fact that city residents and the trucks delivering goods have to travel through other areas to reach the city (and not in tunnels to shield those areas from the traffic noise. etc.)- best called 'new or neo-medievalism.

Such "planning" is what has preceded the developer giveaway of half of the I-395 Center Leg right of way via the "Capitol Crossing" Air Rights Project.
http://wwwtripwithinthebeltway.blogspot.com/2015/01/choking-i-395-center-leg.html

Saturday, December 20, 2014

Current I-395 Center Leg Air Rights ROW PINCH- Shoddy Consideration & Misrepresentations

Developer give-way ZERO consideration of I-395 flexibility
Needlessly assumes I-395 will never have an extension,
nor consideration for an I-66 crosstown tunnel

This right of way PINCH is unreported in every article that I have seen on this project outside of A Trip Within the Beltway.


I-395 Center Leg Capital Crossing right of way pinch
from 4 to only 2 lanes per direction

"Typical I-395 cross section"  page 10 2009 Air Rights EIS

http://wwwtripwithinthebeltway.blogspot.com/2014/12/erased-comments-from-wp-article-dc.html
DDOT's behavior here reeks of behind the scenes deals and bribes.

Their weird silence, stonewalling of the WP requests for information, and then their idiotic stance that since it's part of 395 that they can't weigh in was absurd.

New email message to info@3rdstunnel.com   --  December 12, 2014
I received no reply to my email of November 21, 2014.

Does your project use the designs shown in the 2009 report that pinch the I-395 right of way?

What is the width of the northbound and southbound mainlines once the project is completed?

Facts:

The underground I-395 Center Leg was designed to feature 4 lanes in each direction within the tunnel segments on both the north and the south sides of the open trench that is the site of the current air rights project.

As the segment to the south may have issues of inadequate merge-split lanes it may be viewed as a 3 through lane plus one axillary lane in each direction facility, unless the outer walls are re-located outwards beneath the mall.

However, the northern tunnel being a newer design and with its potential merge area to the north of K Street, is properly an 8 through lane tunnel.



Center Leg trench looking north showing the unused righthand lanes- 
the jersey barrier separates the 3rd lane which is now used as a shoulder from the 4th and rightmost lane which remains in its original concrete with the original right-hand shoulder in asphalt.



Center Leg northbound transition to the southern portal of the northern tunnel segment at Massachusetts avenue- note the non-load-bearing wall coordining the space off for the 2 outer lanes

The North Segment:

The segment to the north, between Massachusetts avenue and K Street NW, was built between 1975 and 1978, with a finishing project from 1983 to 1986.  It features a design for a full 4 lanes in each direction, plus shoulders, plus space for an additional - 5th - northbound lane for a left lane ramp to the planned crosstown I-66 Tunnel that would have been under K Street between Franklin Square and Washington circle.  Additionally it features a separate one lane northbound on ramp that would have merged with the northbound mainline to the north of its northern portal at K Street.   Although what people may see today is only a 2 lane plus shoulder in each direction tunnel, that is only because of walls that were added as part of the 1983-1986 finishing project- as the K Street Tunnel and the I-395 extension to the northeast were both canceled once the initial project was underway. These walls are not load-bearing, as can be seen in the expansion joints visible on the surface of K Street and thus could be easily removed.


Northern Center Leg Tunnel 
showing pair of 3 lane continuations to 1971 plan for freeway extension to the northeast, with pair of one lane connections towards I-66 K Street Tunnel



Note the expansion joints on the surface of K Street marking the load-bearing walls.
Note the unused northbound on-ramp, with its merge area north past the tunnel's portal at K Street.

This design with the 4 southbound lanes and the 5 northbound lanes was designed to connect to a pair of 3 lane connections to the northeast, and a pair of one lane connections to the west.

The South Segment (The Mall Tunnel)

The Center Leg tunnel segment to the south, known as the Mall Tunnel, extending from D Street NW to just south of C Street SW,  was constructed between 1966 and 1973.

Unlike the newer northern tunnel segment, the older southern tunnel segment has no afterthought walls, and features an unobstructed space for 4 lanes in each direction.  The site DCRoads, by Steve Anderson states that each direction is 66 feet wide- which would allow 4 lanes at 12 feet each - 48 feet -- plus 18 feet for shoulders.



That appears to be the case with the northbound carriageway.  It starts at its southern end just south of C Street SW where it intercepts a 3 lane roadway and a single lane on-ramp from D Street SW that converge into a 4 lane roadway just inside the tunnel.   (The 3 lane roadway intercepts a single lane for the I-395 northbound transition from the SW Freeway, and a 2 lane roadway that intercepts one lane apiece from the westbound SE freeway and from South Capitol Street).

These 4 northbound lanes continue northward beneath the Mall before 'loosing' the rightmost lane with the two lane off-ramp at C Street, with the second to right hand lane being an 'indecision' lane where one can take that off-ramp or continue upon the center leg now as the outermost of 3 northbound lanes next to an extra wide shoulder that is subsequently striped as a 4th northbound lane.

Further north in the vicinity of the Mall Tunnel's northern portal at D street NW, the right hand two lanes split off from the mainline to the 2 lane exit ramp at Georgetown Law Center, leaving two northbound lanes in the trench with the space for the 2 additional lanes unused.

The Mall Tunnel's southbound carriageway appears to be somewhat narrower at its northern end beneath the Labor Department Building.   There, it intercepts the two open lanes from the trenchway, picking up a 3rd lane from the southbound on-ramp from 3rd Street, re-aligned from its original design, with an extra wide right-hand shoulder that though marked by an overhead light, is unused as a 4th lane, apparently to provide extra space for the subsequent southbound on-ramp from D Street just south of the labor Department Building.

Ideally, the Mall tunnel should have its walls eventually relocated outwards in the area south of the Labor Building to allow a continuous 5th lane between the southbound on and of ramps, as well as perhaps providing somewhat wider shoulders. Without doing that it may be best viewed as a 6 through lane plus 2 auxiliary lane facility.   If the space beneath the Labor Department Building is considered inadequate for a proper merge area for the on-ramp currently scheduled for reconstruction, than a new design that carries that on-ramp in a separate tube carrying it past the Labor Department Building ought to be considered.  THAT would thus allow maintaining the southbound off-ramp that is to be eliminated by the current air rights project: its elimination is another stupid idea that assumes the freeway shall never be extended.  (Rather, that ramp should be retained.)  Such actions would become more needed once a northern extension from the Center Leg is constructed.

The 2009 Center Leg Air Rights Study fails not only for misrepresenting the Center Leg capacity, but also for assuming that the freeway shall never be extended, nor that an I-66 K Street Tunnel project would never be built.

It fails to consider the feasibility of either project, even as a 1996 design for a New York Avenue tunnel employing that avenue's existing right of way, and shown with 2 lanes in each direction is actually wide enough for 3 lanes in each direction.  That plan, by using the existing right of way beneath New York Avenue, would avoid the displacement of 600+ dwellings along that Avenue's north side between New Jersey Avenue and North Capitol Street.

1996 'Ron Linton' New York Avenue Tunnel proposal for 4 lane tunnel 
within right of way sufficient for 6 lane version

Both the 1996 I-395 extension proposal and the I-66 K Street Tunnel would use existing right of way.

An alternative concept for a tunneled extension arcing beneath the intersection of New Jersey Avenue and N Street and continuing as a double stack beneath O Street meanwhile would only displace about 33 or 34 dwellings while providing vastly superior geometric operationabilty then either the 1971 or 1996 plan.

Yet the 2009 EIS fails to consider flexibility for any of these proposals with its willful and unnecessary pinching of the I-395 Center Leg right of way to a fixed 2 lanes in each direction.  It even pinches the median shoulder, trading away safety, simply to maximize developer profits.

http://wwwtripwithinthebeltway.blogspot.com/2014/12/unanswered-questions-3rd-street-tunnel.html
http://wwwtripwithinthebeltway.blogspot.com/2014/12/erased-comments-from-wp-article-dc.html
http://wwwtripwithinthebeltway.blogspot.com/2007/03/i-66-north-leg-west-k-street-tunnel.html
http://wwwtripwithinthebeltway.blogspot.com/2009/01/i-395-extension

http://wwwtripwithinthebeltway.blogspot.com/2011/02/us-ncpc-perjury-2006.html
If people can get so upset over the recent developer suggestion to entirely shut down the Center Leg segment north of the Labor Department Building, why than should they be so complacent about the permanent giveaway of 50% of its right of way?

And why should this permanent right of way giveaway go so unreported by newspapers as The Washington Post, numerous real estate development blogs, including of course Greater, Greater Washington, which has so far declined A Trip Within The Beltway suggestion to include it in their breakfast links recently?




Thursday, May 14, 2009

A Telling Deletion

About the political influence of
Catholic University of America
and
Masonic Eastern Star
in Blocking PEPCO-B&O
Washington, D.C. I-95
as property holders along the route


Deleted conversation from Imagine DC:

---
Blogger Douglas A. Willinger said...

[Dave Murphy- Imagine D.C. quote]

" Now, I'm not endorsing HOV and HOT lanes (and certainly not any new construction of such roads) as any sort of a cure for our traffic problems here in Washington. But this is a very poignant reminder of how entitled we believe are cars should be. "

[my reply]

In that area?

With that giant gap in the northern radial net and the center hub?!

I do not ever see the original 1955-59 system being built for good reason - aka footprint. Why clear cut trees and or houses when there is a 250 foot wide power line, a rr industrial corridor and a 147 foot wide street to go beneath?

I do see a modified version of the 1971 plan somewhat with a redesigned center section (see "Trip" Nov 2007) with the northern I-95 continuation via the PEPCO route.

But only after something major politically happens about what runs that area (aka that Masonic Eastern Star property [on New Hampshire Avenue near Eastern Avenue], which I am suspicious of given the lack of anything from them about that route or the logical to me option of it as a cut and cover tunnel to preserve the property's dignity.

Likewise with CUA's apparent lack of interest in a deck along the B&O corridor. Please note the 1966 plan proposed it to run north to Taylor Street, but that is deleted by the 1971 plan.

http://wwwtripwithinthebeltway.blogspot.com/2008/05/1966-1971-covered-north-central-freeway.html

And as well that attitudes I have witnessed, aka at the end of the following article; do recall the active participation of the Jesuit Georgetown Law Center in the anti highway crusades.

http://wwwtripwithinthebeltway.blogspot.com/2007/02/sampling-of-attitudes-towards-dc-i-95.html

http://wwwtripwithinthebeltway.blogspot.com/2008/01/physical-realities-undermining-north.html

Knowing my history beyond that of the planning of the D.C. area highways, I see no reason to go along with any sort of white is black and black is white placating (as I witnessed at say college frat parties).

February 28, 2009 5:16 PM


Blogger Dave Murphy said...

Douglas,
I fail to see the relevance of this...

March 1, 2009 3:43 AM

Blogger Douglas A. Willinger said...

You made a strict statement against any new highways in an area with huge gaps in the road network and in common sense.

I think a far better constitutional argument would be the lack of the freeways in the northern sector as placing a disproportionate amount of the traffic burden to the south east of the Anacostia River as classic environmental racism.

Of course Georgetown Law Center apparently would make the situation worse by truncating I-395 at Mass Ave, and with their unjustified influence get their way.

That our government continues with these completely unjustified strict anti freeway policies and boondoggles as street cars while pushing domestic surveillance (while ignoring civil defense) speaks volumes about its nature.

March 1, 2009 9:02 AM

Blogger Dave Murphy said...

I made a passing opposition to new construction of HOT lanes and HOV lanes. Are you saying lack of construction of HOT lanes and HOV lanes is unconstitutional?

I fail to see how any of what you said relates to this post.

March 1, 2009 2:03 PM

Blogger Douglas A. Willinger said...

No, rather the lack of freeways in the northern sector relative to placing the burden where it is, might be.

HOT/HOV lanes though are a good way IMHO to throttle usage, particularly with transfers to WMATA rail parking garages.

Also the tolls are good for funding the extra high dollar designs of cut and cover and drilled tunnels necessary for accommodating a high speed highway in an urban area.

If you search misc.transport.road, my late 1990s advocacy of the PEPCO-B&O route coupled it with a southbound variable rate toll at Fort Totten and rail transfer facility.

March 1, 2009 4:25 PM


Blogger Dave Murphy said...

In the future, I'd appreciate it if you kept the comments focused on the issues presented in the articles I post and save your crusade to have I-95 constructed through NE DC for your own website (unless, of course, it is pertinent to something written about here.) Any further such comments will be deleted.

March 1, 2009 4:35 PM

Blogger Douglas A. Willinger said...

The comment was relevant to this and your preceding post.

I did not see any reason to post it twice.

March 1, 2009 6:45 PM


Blogger Douglas A. Willinger said...

The link to my blog on your blog vanished, though I do not know why.

March 1, 2009 6:47 PM

---

Masonic Eastern Star Home
on New Hampshire Avenue
between railroad and Eastern Avenue


Proposed D.C. I-95
dashed lines indicating connecting segment of
PEPCO power line-B&O route
through Masonic Eastern Star property


1966 D.C. I-95 proposal
with red area of proposed air rights development
extending alongside CUA northwards to Taylor Street

1971 D.C. I-95 proposal
with proposed air rights development extending south from CUA
(leaving area alongside CUA uncovered-
hence preserving the local isolation from the east via the surface railroad)


http://wwwtripwithinthebeltway.blogspot.com/2007/05/1964-north-central-freeway-routing_08.html

http://cos-mobile.blogspot.com/2008/07/homeland-security-goal-would-be-better.html


http://cos-mobile.blogspot.com/2009/05/romish-masonic-religious-drive-against.html

--- added February 1, 2010

Note- contrast the above February 28 - March 1, 2009 conversation with that about 4 months earlier from the comments section reproduced below from my December 17, 2008 article at 'A Trip Within The Beltway' that republished and expanded upon an article by Richard Layman

http://wwwtripwithinthebeltway.blogspot.com/2008/12/under-selling-b-metropolitan-branch.html

6 comments:

Dave Murphy said...

I think burying the Metropolitan Branch is a fantastic idea, and making it multi-modal would be great. But I have my typica question: where would the freeway end? I don't see it getting to the Beltway through Silver Spring, considering all the high density development along the tracks. I can't imagine they'd approve the Fort Totten Park alignment because it would still tear out a good bit of Chillum before it hits the Beltway. I certainly hope you aren't recommending another dead end freeway!

Douglas A. Willinger said...

The plan would have I-95 split from the rr as a cut and cover tunnel beneath the field of the Masonic Eastern Star Home alongside NH Avenue, displace about 27 brick houses just inside DC and then 13 strip retail properties (with a monumental traffic circle at the DC-MD line, and then some cut and cover in MD with new development atop); there is no reason to use the Fort Totten (Fort Drive) Park route with the existence of the NHA-PEPCO route.

It could and should include the Silver Spring segment, either by ripping out some of the misplaced development on the rr's eastern side, or even a segment as drilled tunnel.

It would not displace the historic Cady Lee Mansion in TP, nor the houses facing the rr along Takoma Avenue, though it would take some of the misplaced Montgomery Gardens apartment complex.

Grade requirements will require placing the heavy rr in a drilled tunnel to northwest of 16th Street, but the WMATA could stay upon the existing Georgia Avenue overpass, which could have a surface street placed on it where the heavy rr is to better connect the area locally.

Some of Cedar Crossing might have to go, along with the entire Elevation 314 building.

However a replica of the historic TP rr station could and should reappear in a new Takoma Station Town Square.

Douglas A. Willinger said...

Please see:

https://blogger.googleusercontent.com/img/b/R29vZ2xl/AVvXsEhVmqBLaso6uklFbH8gB_MlvwZn31Un448Yia3Zolm7126DvcmJd70vRDGxn25SoY9HZpghUh6oKrBtxoFcuhyQrqO2iXRwGNTFfKmha9JQsiPnTbVtkjNXKM2Tig_4AAHbRkfT/s1600-h/Takoma_Station_Tunnel.JPG

Douglas A. Willinger said...

The above url may not be readable; it is the illustration in this blog's post of July 2007:

http://wwwtripwithinthebeltway.blogspot.com/2007_07_01_archive.html

try this blog's tag "Grand Arc Mall Tunnel"

http://wwwtripwithinthebeltway.blogspot.com/search/label/Grand%20Arc%20Mall%20Tunnel

Also see the 2 redundant tags about the B&O rr corridor.

Dave Murphy said...

the PEPCO route seems to be logical, reconnecting at College Park's interchange, I presume. I also imagine it would be two lanes in each direction, and above the railroad ROWs?

I'm a huge fan of burying the Metropolitan Branch, but I have never seen any sort of an estimate for how much it would cost to do so, and what kind of service interruptions the red line, MARC, and CSX would face during reconstruction.

Douglas A. Willinger said...

The rail lines would first be replaced to avoid service interruptions, before the removal of the existing rail lines and the construction of the underground highway.